  1. The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
  2. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be A. 50 % B. Less than 50 % C. More than 50 % D. 100 %
  3. The direct cost of a project with respect to normal time is
  4. Whenever an activity has zero total float, then
  5. While filling the tender for any work, the contractor considers
  6. Railway projects are treated as
  7. If the excavation of earth is done manually then it costs Rs. 10 per cum. A machine can excavate at a fixed cost of Rs. 4000 plus a variable cost of Rs. 2 per cum. The quantity of earth for which the cost of excavation by machine will be equal to the cost of manual excavation is
  8. Construction team means
  9. Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same
  10. The time which results in the least possible construction cost of an activity, is known as
  11. The area under the Beta distribution curve is divided into two equal parts by
  12. The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to
  13. Which one of the following is not an excavating and moving type of equipment?