The correct answer is D. parallel.

In a parallel implementation, the old system and the new system are run at the same time for a specified period. This allows users to compare the two systems and make sure that the new system meets their needs. It also allows the organization to switch to the new system without disrupting business operations.

A direct implementation is a type of system implementation in which the new system is put into place immediately, without any testing or preparation. This is a risky approach, as it can lead to problems if the new system is not compatible with the old system or if users are not trained on how to use it.

A pilot implementation is a type of system implementation in which the new system is tested with a small group of users before it is put into place for everyone. This is a less risky approach than a direct implementation, as it allows the organization to identify and fix any problems before the new system is rolled out to everyone.

A phased implementation is a type of system implementation in which the new system is put into place in stages. This is a less risky approach than a direct implementation, as it allows the organization to test the new system in stages and make changes as needed.

E is not a valid option.