You’re using Critical Path Method (CPM). A task has an early start (ES) of 4 and late start (LS) of 10. What is the slack?
Asked in GPSC Assistant Director (IT), Class-1 2025
Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.