18 Rajender engages Sunil and Vijay to do some construction work in his office. Sunil is highly skilled and is 3 1/2 times as good a workman as Vijay. Therefore, he is able to finish his work in 45 days less than Vijay. In how many days they both working together, can finish the work?

Asked in HPSC HCS (Ex.Br.) & Other Allied Services Preliminary Exam CSAT 2023

  1. 26 days
  2. 22 days
  3. 18 days
  4. 14 days
  5. Question not attempted
Show answer

Answer: D. 14 days