In job-shop scheduling, 1. Shortest Processing Tim...
Guiding State PSC aspirants since 2016 50,000+ students · 1,000+ final selections Exam Calendar Results Call 9116926003
pscnotes
Pick your state
GPSC Prelims previous year questions

In job-shop scheduling, 1. Shortest Processing Time (SPT) minimizes average flow time. 2. Earliest Due Date (EDD) minimizes maximum lateness. 3. First-Come-First-Serve minimizes tardiness variance. 4. Critical Ratio rule maximizes machine utilization. Select the correct option from below.

Asked in GPSC Assistant Industry Commissioner, Class-1, Gujarat Industrial Service 2026

  1. 1 and 2 only
  2. 2 and 3 only
  3. 3 and 4 only
  4. None of the above

Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.