Consider the following statements: Statement I: A Master Production Schedule is a long-term strategic plan. Statement II: A Master Production Schedule serves as an input to Material Requirements Planning (MRP). Statement III: A Master Production Schedule specifies what, how much and when to produce finished goods. Which of the above statements are correct?

Asked in GPSC Graduate Engineer Trainee, Class-2, Gujarat Maritime Board (GMB) 2026

  1. I and II only
  2. II and III only
  3. I and III only
  4. I, II and III
Show answer

Answer: B. II and III only