Which of the following best describes the concept of "scope creep" in project management?

Asked in GPSC Gujarat Water Supply and Sewerage Board Engi. Service (Mechanical) 2025

  1. The intentional addition of project features as agreed upon by stakeholders.
  2. The gradual increase in project scope without corresponding increases in resources or time.
  3. The process of refining the project scope during the planning phase.
  4. The expansion of project boundaries to align with initial project goals.