The plan of a building is in the form of a rectangle with center line dimensions of outer walls as 12.7 m × 15.7 m. If the thickness of the wall in superstructure is 0.30 m, then its plinth area (in m2) is
Asked in GPSC Gujarat Engineering Service (Civil), Class-1 and Class-2 2026
Answer under review: our editors are checking this question. Try the other GPSC Prelims previous year questions questions meanwhile.
More GPSC Prelims previous year questions questions
- A concrete batching plant was purchased 6 years ago for Rs. 50 lakhs. The company uses the straight-line depreciation method with an assumed useful life of 10 years and a scrap value of Rs. 5 lakhs. The current market value of the plant is Rs. 18 lakhs. Which of the following statements is correct?
- The type of estimate used for fixing up the value of the project for the insurance and tax schedule requirements is
- The architect, after consulting the client, invites a few contractors to submit tenders. This is called
- The success of the construction activities largely depends upon (i) Time and money (ii) Machinery and materials (iii) Skilled and unskilled manpower
- Which of the following statement(s) is/are true for ‘Dangling Error’? (i) A dangling error in a project network diagram (CPM/PERT) occurs when an activity is disconnected or hangs before the project's final event. (ii) Dangling error represents broken logic where an activity has no successor, making it appear to finish before the overall project is complete.
- Which of the following statement(s) is/are true? (i) Reconnaissance survey is conducted to get an idea about the terrain and any special and difficult features that may be encountered during a regular survey (ii) More precise instruments and methods are used for reconnaissance survey
- In land surveying, the method of triangulation is preferred over traversing primarily when
- A hydrographic survey is to be conducted in a tidal river to prepare a navigation chart. The reduced level of the water surface at a given time is obtained by