Which of the following statement(s) is/are true for resource levelling? (i) The project completion time is not extended even though there is a constraint in the availability of resources (ii) Start of the non-critical activities is delayed
Asked in GPSC Engineering Aptitude 2024
Show answer
Answer: B. Only (ii)
This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.
More GPSC Prelims previous year questions questions
- At 9:30, the hour hand and minute hand of the clock will form an angle of
- Which of the 4 components are contributing to Tetralogy of Fallot?
- Mr. X has Above Knee Amputation. Which of the following statement is not considered as facilitator of his mobility according to ICF?
- A 9-year-old boy presented with an increasing difficulty in walking and running in the school. The boy started walking at the age of 20 months. By the age of 7 years, he assumed a lordotic posture and frequent falls while playing with his peers. He walks with a wide base of support and has extreme difficulty to stand from the floor. He has a 7-year-old sister with normal development. Which of the following statement is incorrect about his condition?
- In surgical approaches of Arthroplasty, the use of minimally invasive surgery is becoming popular because of
- Regarding the flow of Cerebrospinal fluid, which one of the following sequence is correct?
- Which of the following statement is CORRECT regarding cardiac cycle?
- Little’s disease is popularly known as