A and B can do a piece of work in 24 days, while B and C can do it in 16 days whereas A and C can do it in 12 days. How many days will ‘A’ take to do the same work? (A) 24 days (B) 36 days (C) 30 days (D) 32 days (E) Answer not known

Asked in TNPSC Tamil Eligibility Test & General Studies Tamil Eligibility Test & General Studies 2026

  1. 24 days
  2. 36 days
  3. 30 days
  4. 32 days
  5. Answer not known
Show answer

Answer: B. 36 days