A and B together can do a piece of work in 12 days while B alone can finish it in 30 days. A alone can finish the work in

Asked in Mizoram PSC 2.UDC under EF&CC Deptt. Paper-II

  1. 15 days
  2. 20 days
  3. 21 days
  4. 22 days
Show answer

Answer: B. 20 days