A bridge is to be constructed in three phases. 2/9 part of the bridge was completed in phase I and 5/14 part in phase II. How much part of the bridge remains to be completed in phase III?

Asked in Mizoram PSC 2.UDC under SAD Paper-II

  1. 53/126
  2. 43/126
  3. 9/14
  4. 7/9
Show answer

Answer: A. 53/126