A can do a piece of work in 10 hours, while B can do the same work in 6 hours. B worked at it for 4 hours. How long will A take to finish the remaining work?

Asked in Mizoram PSC 2.UDC Paper-II

  1. 3 hours
  2. 3 hours 20 minutes
  3. 3 hours 50 minutes
  4. 5 hours
Show answer

Answer: B. 3 hours 20 minutes