A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work left is -

Asked in Mizoram PSC 2.UDC Paper-II

  1. 1/4
  2. 1/10
  3. 7/15
  4. 8/15
Show answer

Answer: D. 8/15