A does 80% of a work in 20 days. He then calls B and they together finish the remaining work in 3 days. How many days B alone would take to do the whole work?

Asked in APSC General Studies

  1. 29 days
  2. 34½ days
  3. 36½ days
  4. 37½ days
Show answer

Answer: D. 37½ days