A PERT network has 9 activities on its critical path. The standard deviation of each activity on the critical path is 3. The standard deviation of the critical path is

Asked in GPSC Provisional Key (Prelim) - 25/-23 Paper-2 2022

  1. 3
  2. 9
  3. 81
  4. 27