A project is expected to take 15 months along the critical path, having standard deviation of 3 months, what is the probability of completion of project in 12 months?

Asked in TNPSC Town and Country Planning (Subject Code 382)

  1. 15.87%
  2. 84.13%
  3. 50%
  4. 66.6%
  5. Answer not known