A purchasing department finds that supplier manufacturing time has remained stable, while the total time between placing an order and making the materials available for use has increased. Which combination most plausibly account for the increase?

Asked in Kerala PSC General Manager (Project) Part-I -Kerala State Co-operative Coir Marketing Federation Ltd Question Paper Code: 176//OL Category Code: 103/2025 Exam: General Manager (Project) Part-I Date 2026

  1. Longer transportation time and additional inspection/receiving delays
  2. Shorter transportation time and faster inspection procedures
  3. Reduced internal processing time and improved received efficiency
  4. Earlier order placement and reduced supplier production time
Show answer

Answer: A. Longer transportation time and additional inspection/receiving delays