A works 3 times faster than B and completes a work...
Guiding State PSC aspirants since 2016 50,000+ students · 1,000+ final selections Exam Calendar Results Call 9116926003
pscnotes
Pick your state
TNPSC Prelims previous year questions

A works 3 times faster than B and completes a work in 24 days less than the days taken by B. If they both work together, find the time they would take to complete the work.

Asked in TNPSC General Studies with General Tamil (Subject Code 002)

  1. 6 days
  2. 7 days
  3. 8 days
  4. 9 days
  5. Answer not known
Show answer

Answer: D. 9 days

More TNPSC Prelims previous year questions questions

All 17,707 TNPSC Prelims previous year questions questions →