Anil and Suman together can do a work in 12 days, which Anil alone can do in 20 days, If Suman alone has to do this work, he will take

Asked in BPSC 67th (re-exam) Prelims

  1. 28 days
  2. 29 days
  3. 30 days
  4. 27 days
  5. None of the above/More than one of the above
Show answer

Answer: C. 30 days