Choose the correct statement from the following : Comprehensive errors may be caused due to (i) Incorrect holding of arrows (ii) Incorrect plumbing (iii) Not applying sag correction (iv) Not applying slope correction
Asked in TNPSC TRADE - SURVEYOR (Subject Code 387)
Show answer
Answer: B. (i) and (ii) only
More TNPSC Prelims previous year questions questions
- When the chain is too long, it is adjusted by?
- The distance between two points measured by 20 m chain was recorded as 720 meter. But the chain is 4 cm too long. So correct true distance is
- Select the correct statement of measuring short distances in chain survey
- The surveys which are carried out to prepare maps of antiquities are called
- As per is specification limits of error for every meter length in chain should be accurate to within ± 2 mm when measured within tension of ______ kg.
- The preliminary inspection of the whole area of the site to be surveyed is known as
- In metric chain, the links are composed of pieces of galvanised mild steel wire of
- The length of a line measured with a 20 metre chain was found to be 250 metre. Calculate the true length of the line if the chain was 10 cm. Too long