Concession Period in BOT contract is the period of ______

Asked in GPSC Soil Survey Officer, Class-I 2024

  1. Time required for construction of facility
  2. Time required for maintenance of facility
  3. Time required to recover the cost incurred by the contractor
  4. Time required to complete the project
Show answer

Answer: C. Time required to recover the cost incurred by the contractor