Critical path in Activity network of Software project management is

Asked in Mizoram PSC 4.Technical Paper-II

  1. The longest path from start to finish (The maximum time required to complete the project)
  2. The shortest path from start to finish (The minimum time required to complete the project)
  3. The mean time required to complete the project
  4. None of the above.