Diversion head work is constructed to

Asked in GPSC Deputy Soil Survey Officer, Class-II 2024

  1. Facilitate the silt entry into the canal
  2. Lower water level in the river
  3. Increase fluctuations in the supply level of the river
  4. Regulate the intake of water into the canal
Show answer

Answer: D. Regulate the intake of water into the canal