For cooling of adjoining flammable liquid tanks, additional quantity of water shall be provided at the rate of 10 LPM / m² of exposed surface of the next tank, for a period of at least ______: (A) 4 hours (B) 3 hours (C) 2 hours (D) 1 hours

Asked in GPSC Assistant Director/Regional Fire Officer, Class-1 under the Directorate of Gujarat State Fire Prevention Service 2023

  1. 4 hours
  2. 3 hours
  3. 2 hours
  4. 1 hours
Show answer

Answer: D. 1 hours