If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, what is the time taken by 15 men and 20 boys to complete the same work?

Asked in GPSC Assistant Conservator of Forest, Class-2 2022

  1. 6 days
  2. 7 days
  3. 4 days
  4. None of the above
Show answer

Answer: A. 6 days