If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is

  1. $$\frac{{{\text{a}} + {\text{m}} + {\text{b}}}}{6}$$
  2. $$\frac{{{\text{a}} + 2{\text{m}} + {\text{b}}}}{6}$$
  3. $$\frac{{{\text{a}} + 4{\text{m}} + {\text{b}}}}{6}$$
  4. $$\frac{{{\text{a}} + 5{\text{m}} + {\text{b}}}}{6}$$

Answer under review: our editors are checking this question. Try the other Construction planning and management questions meanwhile.