In a construction project, "Parallel Activities" are those activities which can be performed:-

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Civil Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. One after the other and are dependent on each other
  2. One after the other and are independent of each other
  3. Simultaneously and are dependent on each other
  4. Simultaneously and are independent of each other
Show answer

Answer: D. Simultaneously and are independent of each other