In a high head hydroelectric power station, a surge tank is provided to

Asked in GPSC Provisional Key (Prelim) - 98/-21 PAPER 1 AND PAPER 2 2020

  1. reduce the length of penstock
  2. control pressure variations in the penstock due to sudden load changes
  3. augment water at forebay
  4. control the water flow through turbine