In a Materials Requirements Planning (MRP I) system, which document lists all the components, sub assemblies and raw materials, along with the quantities needed, to produce one unit of a finished product?

Asked in Kerala PSC General Manager (Project) Part-I -Kerala State Co-operative Coir Marketing Federation Ltd Question Paper Code: 176//OL Category Code: 103/2025 Exam: General Manager (Project) Part-I Date 2026

  1. Master Production Schedule (MPS)
  2. Bill of Materials (BOM)
  3. Inventory Record File
  4. Purchase Order
Show answer

Answer: B. Bill of Materials (BOM)