In case of a framed RCC Construction, the form work to be removed first are :-

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Civil Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. Bottom of beams
  2. Bottom of roof slab
  3. Sides of beams
  4. Any of Bottom of beams or Bottom of roof slab
Show answer

Answer: C. Sides of beams