In CPM, the project duration can be reduced by crashing

Asked in GPSC Principal, Class-2 Labour and Employment Department 2024

  1. One or more critical activity only
  2. One or more non-critical activity only
  3. One or more dummy activity only
  4. Activity having independent float
Show answer

Answer: A. One or more critical activity only