In India, hydro power projects are classified according to their capacity to produce the power. Then choose the correct answer.

Asked in KPSC Prelims 2014 KAS August Paper 2

  1. micro hydro power project : upto 300 kW, mini hydro power project : 301 to 3000 kW, small hydro power project : 3001 to 30000 kW
  2. micro hydro power project : upto 200 kW, mini hydro power project : 201 to 1000 kW, small hydro power project : 1001 to 5000 kW
  3. micro hydro power project : upto 500 kW, mini hydro power project : 501 to 5000 kW, small hydro power project : 5001 to 30000 kW
  4. micro hydro power project : upto 100 kW, mini hydro power project : 101 to 2000 kW, small hydro power project : 2001 to 25000 kW
Show answer

Answer: A. micro hydro power project : upto 300 kW, mini hydro power project : 301 to 3000 kW, small hydro power project : 3001 to 30000 kW

This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.