In project evaluation, what does the pay back period measure (A) The total time taken to complete a project (B) The time required to recover the initial investment (C) The time it takes for a project to break even (D) The annual rate of return generated by a project (E) Answer not known

Asked in TNPSC Associate Company Secretaryship (Final) (Subject Code 473)

  1. The total time taken to complete a project
  2. The time required to recover the initial investment
  3. The time it takes for a project to break even
  4. The annual rate of return generated by a project
  5. Answer not known
Show answer

Answer: B. The time required to recover the initial investment