In the analysis of rates, the profit for contractor is taken as
Asked in GPSC Soil Survey Officer, Class-I 2024
Show answer
Answer: C. 10%
More GPSC Prelims previous year questions questions
- Tax generally not applicable to residential building is
- Damages caused due to delay in work are termed as ______
- If any extra items are to be executed as a result of change in design, rate for such items are derived from ______
- A notice inviting vendors to participate in pre-qualification process is formally called as ______
- Earnest Money Deposit (EMD) can not be submitted in ______ form
- Which contract condition specifies contractors liabilities for maintenance of work?
- Which contract conditions specifies rate of extra work to be done by contractor?
- When contractor is only supplying materials then such contracts are called as ______