In the context of environmental planning for mining activities, what is the required extent of the buffer zone measured from the periphery of the core zone for a Mining Lease (ML) area of 40 hectares?

Asked in GPSC Town Planner, Class-1, (New Municipal Corporations)/ Junior Town Planner, Class-2, (New Municipal Corporations) 2026

  1. 2 km
  2. 5 km
  3. 10 km
  4. 15 km
Show answer

Answer: C. 10 km