Once a tender is accepted, a deposit of about 5% of the total estimated cost of the work is called:
Asked in GPSC Provisional key (Prelim) - 40/2017-18 General Studies & Concerned Subject 2018
Show answer
Answer: B. security deposit
More GPSC Prelims previous year questions questions
- At the time of opening of the tenders invited for public works by a public body,
- Kinematic viscosity has the dimension as
- The resultant hydrostatic force on a submerged body acts through a point known as
- In steady flow
- In a venturimeter installed in a horizontal pipe the pressure is maximum at
- The velocity distribution in laminar flow through circular pipe follows
- Froude’s number is the ratio of
- The model and prototype are dynamically similar if both the systems have