Ques #: 30 All activities lying on critical path have slack time equal to 1) 0 2) 1 3) 2 4) None of thses

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Information Technology)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. 0
  2. 1
  3. 2
  4. None of thses