Ques #:41 If the line of action of the resultant forces on the dam lies outside the middle third of the base, then the dam is susceptible to :- 1) Crushing failure 2) Tension failure 3) Sliding failure 4) Overturning failure

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Civil Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. Crushing failure
  2. Tension failure
  3. Sliding failure
  4. Overturning failure
Show answer

Answer: B. Tension failure