Ques # :57 A generating station has a maximum demand of 50 MW, a load factor of 60 %, a plant capacity factor of 45 %. If the plant while running is fully loaded, the daily energy produced will be:

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Electrical Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. 400 MW
  2. 720 MW
  3. 500 MW
  4. 600 MW
Show answer

Answer: B. 720 MW