Ques #: 71 Waterfall model is not suitable for:- 1) Complex project 2) Small project 3) Accommodating project 4) None of these

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Computer Science)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. Complex project
  2. Small project
  3. Accommodating project
  4. None of these
Show answer

Answer: A. Complex project