Ques # :90 In PERT the span of time between the optimistic and pessimistic time estimates of an activity is 1) 6σ 2) 3σ 3) 12σ 4) σ

Asked in RPSC 23Feb 2016Question Paper for VicePrincipal/Superintendent ITI Screening Test 2012(Mechanical Engineering)VICE PRINCIPAL/SUPDT. ITI - 2012

  1. 6σ
  2. 3σ
  3. 12σ
  4. σ
Show answer

Answer: A. 6σ