Ques #:99 Which of the following charts is useful in scheduling? 1) Gantt chart 2) Outline process chart 3) Flow process chart 4) SIMO chart

Asked in RPSC 02Jun 2016Question Paper for Asst. Engineer (Mechanical) GWD Screening Test - 2014ASST. ENGINEER - 2014

  1. Gantt chart
  2. Outline process chart
  3. Flow process chart
  4. SIMO chart

Answer under review: our editors are checking this question. Try the other RPSC Prelims previous year questions questions meanwhile.