Rajender engages Sunil and Vijay to do some constr...
Guiding State PSC aspirants since 2016 50,000+ students · 1,000+ final selections Exam Calendar Results Call 9116926003
pscnotes
Pick your state
HPSC Prelims previous year questions

Rajender engages Sunil and Vijay to do some construction work in his office. Sunil is highly skilled and is 3 times as good a workman as Vijay. Therefore, he is able to finish his work in 45 days less than Vijay. In how many days they both working together, can finish the work?

Asked in HPSC Prelims 2023

  1. 26 days
  2. 22 days
  3. 18 days
  4. 14 days
  5. (E) Question not attempted
Show answer

Answer: D. 14 days

More HPSC Prelims previous year questions questions

All 3,478 HPSC Prelims previous year questions questions →