Ten men can finish construction of a wall in eight days. How many men are needed to finish the work in half – a – day?

Asked in Mizoram PSC 8.MCS Series D Paper-II

  1. 80
  2. 100
  3. 120
  4. 160
Show answer

Answer: D. 160