Ten men can finish construction of a wall in eight days. How many men are needed to finish the work in half – a – day?
Asked in Mizoram PSC 8.MCS Series D Paper-II
Show answer
Answer: D. 160
More MPSC Prelims previous year questions questions
- The average height of students in a class of 10 is 105 cm. If 20 more students with an average of 120 cm join the class, what will the average height be.
- A one rupee coin is placed on plain paper. How many coins of the same size can be placed round it so that one touches the central and adjacent coins?
- Five persons A,B,C,D and E are sitting on a row facing you such that D is on the left of C and B is on the right of E. A is on the right of C and B is on the left of D. If E occupies a corner position, then who is sitting in the centre?
- A number is made of 2 digits. If 45 is added to the number, the digit gets reversed. What is the number?
- A boy remarked that he has twice as many sisters as he has brothers. One of the sisters replied, “that’s funny, because I have just as many sisters as brothers”. How many boys and how many girls are there in the family?
- A man started walking west; he turned right, then right again and finally turned left. In what direction was he walking?
- In which of the following situations should an employee use his own judgment?
- The best method of training an inexperienced worker to perform a task is to