The correct answer is: B. Rs 1.31

The budget variable cost per unit can be calculated as follows:

Budgeted variable cost per unit = (Budgeted total variable cost - Budgeted fixed cost) / Budgeted output

= (300,000 - 87,000) / 162,500

= Rs 1.31

The other options are incorrect because they do not take into account the budgeted fixed cost.