The amount of time by which the start of the activity may be delayed without interfering with the start of any succeeding activity in CPM network is called
Asked in Mizoram PSC 12 Jr.Grade of MES (Civil) (Contract) under DM&RD 20151.General English2.General Studies3. Engineering Paper I4. Engineering Paper II5. Engineering Paper III
Show answer
Answer: B. Free float
This previous-year question came without the commission's answer key; the answer was checked by AI. Always confirm with the official key.
More MPSC Prelims previous year questions questions
- The first stage of a construction is
- The continuity equation of fluid flow is the mathematical statement of
- Which of the following plays significant role for fluid to flow in laminar type?
- Superflous variables in dimensional analysis are
- The change of physical property in isothermal process is governed by
- If Mach Number is slightly less than or slightly greater than 1, then the flow is termed as
- Hydrostatic pressure on a dam depends upon its
- Since stream line is everywhere tangent to the velocity vector