The estimated time required to perform an activity, is known as

Asked in APPSC (Arunachal) GENERAL KNOWLEDGE(WRITTEN EXAM)

  1. Event
  2. Dummy
  3. Duration
  4. Float
Show answer

Answer: C. Duration