The correct answer is C. To keep the project cost within the cost budget and knowing when and where job costs are deviating.

The key to profitable operation for project cost control is to keep the project cost within the cost budget and knowing when and where job costs are deviating. This means that the project manager must have a clear understanding of the project's budget and be able to track actual costs against the budget on a regular basis. If costs are starting to deviate from the budget, the project manager must take action to correct the situation. This may involve making changes to the project plan, reallocating resources, or negotiating with vendors.

Option A is incorrect because it is not possible to always keep the project cost equal to the original cost estimate. There are many factors that can affect project costs, such as changes in scope, changes in market conditions, and unexpected problems.

Option B is incorrect because the subsequent construction budget may not be accurate. The subsequent construction budget is based on the original cost estimate, which may not be accurate due to the factors mentioned above.

Option D is incorrect because it does not provide a specific answer to the question.