To complete some work, A takes half time than B. C completes same work in same time in which both A and B complete together. If all three together complete this work in 7 days, then in how much days will C complete this work alone ?

Asked in RPSC Junior Accountant and TRA - 2013 Paper-I

  1. 14 days
  2. 42 days
  3. 21 days
  4. 35 days
Show answer

Answer: C. 21 days